BRO rebuilds washed-out Sikkim bridge in 5 days, restoring vital road link

Published on: 05 Jul 2026, 05:55 AM
BRO rebuilds washed-out Sikkim bridge in 5 days, restoring vital road link

The Border Roads Organisation (BRO) restored a crucial road link in Sikkim's Dzongu constituency on Saturday by constructing a bailey bridge over Phee Chu Khola, just five days after the existing bridge was washed away by heavy rainfall.

The bailey bridge in Dzongu was damaged on June 28 due to overnight heavy rain, cutting off the area from the rest of the state. The Phidang-Sankalang stretch remained impassable for five days, disrupting the movement of residents, vehicles, essential supplies, and emergency services.

To restore connectivity, the 107 Road Construction Company (RCC), GREF, under the 758 Border Roads Task Force (BRTF) of Project Swastik, constructed a new bailey bridge adjacent to the damaged structure. Despite continuing rain, difficult terrain, and challenging working conditions, BRO personnel worked round the clock to complete the bridge in five days.

The bridge was inaugurated by Forest Minister and Dzongu MLA Pintso Namgyal Lepcha in the presence of Mangan Deputy Commissioner Anant Jain, Superintendent of Police of Mangan district LB Chettri, Brig Amit Sakhre (Chief Engineer of Project Swastik), BRO officials, and local residents.

Addressing the gathering, Forest Minister Lepcha expressed gratitude to the engineers, labourers, and BRO personnel involved in the project for their dedication and swift execution. 'I sincerely thank the labourers, engineers and the entire BRO team. Completing such a project within such a short period was something we did not expect,' he said.

With the monsoon season under way, the minister noted that more weather-related disruptions could occur, but added that the successful completion of the bridge had reinforced confidence in the BRO's ability to respond swiftly during emergencies. 'There may be many more challenges during the monsoon, but after witnessing the dedication and efficiency of the BRO, we are grateful for their service,' he said.

The minister clarified that the bailey bridge is a temporary arrangement to restore connectivity and announced that a permanent bridge would be constructed after the monsoon season. 'This is only a temporary bridge. Once the monsoon is over, a permanent bridge will be built. In the days ahead, we will collectively work for the development and safety of this area,' he added.

The restoration of the road has brought major relief to the people of Dzongu by resuming the movement of commuters, public transport, essential commodities, and emergency services.